News Search

Team Scott’s runway upgrades completed

Digging holes

Contractors complete the flight line revitalization project at Scott Air Force Base, Ill., Oct. 15, 2020. Enhancing mission capability, the project included upgrading the approach lighting system, as well as repairing and repainting the runway. (U.S. Air Force photo by Airman Isaac Olivera)

Digging holes

Contractors complete the flight line revitalization project at Scott Air Force Base, Ill., Oct. 15, 2020. Throughout the project, the 375th Operations Group still maintained over 20,000 flight operations. (U.S. Air Force photo by Airman Isaac Olivera)

Man using piledriver

A contractor pile drives into the ground at Scott Air Force Base, Ill., Oct. 15, 2020. During the project, flying operations continued without interruption by using the adjacent runway at MidAmerica St. Louis Airport. (U.S. Air Force photo by Airman Isaac Olivera)

Runway

Contractors work on the ramp portion at Scott Air Force Base, Ill., Oct. 15, 2020. The project cost an estimated $16 million and focused on upgrading the approach lighting system. (U.S. Air Force photo by Airman Isaac Olivera)

Man talking

Richard Hupp, 375th Operation Support Squadron airfield manager talks to an airfield system technician at Scott Air Force Base, Ill., Nov. 20, 2020. The new approach lighting system will improve safety flight operations, and allow Team Scott to support more operations for the future. (U.S. Air Force photo by Airman Isaac Olivera)

Aircraft landing

Pilots of a C-21 Learjet test landing on the newly revitalized runway using a Beechcraft B300 King Air at Scott Air Force Base, Ill., Nov. 20, 2020. The landing tested a new lighting system that costs an estimated $16 million will help Team Scott to support more operations and continue to provide global mobility for the future. (U.S. Air Force photo by Airman Isaac Olivera)

Heathman talking

Col. J. Scot Heathman, 375th Air Mobility Wing commander, delivers remarks at a ribbon cutting ceremony for the runway, Nov. 30, 2020 at Scott Air Force Base, Ill. The project included upgrades to lighting and overall repair allowing Team Scott enhanced mission capabilities with use of the runway. (U.S. Air Force photo by Senior Airman Greg Erwin)

Ribbon cutting

U.S. Air Force Senior Airman Samir Ragih, 375th Operations Support Squadron and Staff Sgt. Shena Emmanuel, 375th Civil Engineer Squadron cut a ribbon signifying completion of a flight line revitalization project, Nov. 30, 2020 at Scott Air Force Base, Ill. The runway upgrades took approximately 20 months to complete. (U.S. Air Force photo by Senior Airman Greg Erwin)

Aircraft taxis

A C-21 Learjet taxis on the newly finished runway, Nov. 30, 2020 at Scott Air Force Base, Ill. After completion of a $16 million project, the revitalized runway was cleared to resume operations, enhancing mission capability. (U.S. Air Force photo by Senior Airman Greg Erwin)

Group photo
PHOTO DETAILS  /   DOWNLOAD HI-RES 10 of 10

Members of Team Scott’s leadership and representatives for the runway repair project pose for a group photo, Nov. 30, 2020 at Scott Air Force Base, Ill. Members from the 375th Operations Support Squadron, 375th Civil Engineer Squadron, 375th Contracting Squadron and the MidAmerica St. Louis Airport were crucial components to keep the mission going during the project. (U.S. Air Force photo by Senior Airman Greg Erwin)

SCOTT AIR FORCE BASE, Ill – A ribbon cutting ceremony was held Nov. 30 celebrating the completion of construction on the flight line at Scott Air Force Base. The construction was a part of a flight line revitalization project allowing Team Scott to maintain its presence as Air Mobility Command’s Showcase Wing.

Construction started in April 2019, resulting in temporary closure of the western runway. However, Team Scott still was able to maintain battle readiness, and complete over 20,000 flight operations utilizing MidAmerica St. Louis Airport’s runway.

“The airfield is the largest weapon system on Scott AFB,” said Richard Hupp, 375th Operations Support Squadron airfield manager. “Without an operational airfield, the Air Force motto of ‘fly, fight and win’ cannot occur.” 

The construction project cost an estimated $16 million, and focused on upgrading the approach lighting system to improve safety of flight operations.    

“The airfield underwent a complete lighting system upgrade to high intensity approach lighting with sequence flashers,” said Hupp.

With this new lighting system and other upgrades, Team Scott can support more operations and continue to provide global mobility for the future.

“This is more than just a lighting project. The team repaired concrete, sinkholes, taxiways, repainted most of the runway and today, we get to enjoy the fruits of our labor,” said Col. J. Scot Heathman, 375th Air Mobility Wing commander. “Thank you to the 375th Operations Support Squadron, 375th Civil Engineer Squadron and the 375th Contracting Squadron for making this project happen. Additionally, thank you to the MidAmerica St. Louis Airport for all their support throughout this project.”